Belgium, Brussels: Network issues

Resolved
Resolved

We've now resolved the incident. Thanks for your patience.

Avatar for
Identified

The remote hands team is currently on-site replacing the faulty network component in our Brussels datacenter. While we don’t have an exact ETA, resolution is progressing and we expect connectivity to be restored as soon as possible.

Avatar for
Identified

Our team is on it. It is very isolated, all machines are up, only one hostnode partially lost uplink connectivity. Should not take too long to fix.

Avatar for
Investigating

We are currently experiencing a network outage affecting one of our host nodes located in Belgium, Brussels. Our engineering team is actively investigating the issue and working to restore full connectivity as quickly as possible.

Customers hosted on the affected node may experience connectivity issues or degraded performance.

We apologize for the inconvenience and appreciate your patience.

Avatar for Iztok Zavcer
Iztok Zavcer
Began at:

Affected components
  • KVM Europe
    • Belgium, Brussels